To post a group of transactions, use a cutoff date. Sage 100 Contractor posts all transactions through the indicated date.
Important! If you want to post to a different period, you must change the posting period.
1 | Open 3-11 Recurring Receivables. |
2 | On the Post menu, click Multiple Invoices. |
3 | The Posting Cutoff window appears. |
4 | In the Cutoff Date box, enter the cutoff date, and click OK. |