Working with 4-Accounts Payable > 4-2 Payable Invoices & Credits > Verifying contract balances

Verifying subcontract balances

When saving a payable invoice for a vendor, Sage 100 Contractor refers to the Set Over Subcontract Warning option to determine if the invoice amount exceeds the subcontract balance. If the payable invoice does exceed the balance, Sage 100 Contractor provides you with a warning.

Notes:

To verify subcontract balances:

1 Open 4-2 Payable Invoices/Credits.
2 Select Options, then select Set Over Subcontract Warning.
3 In the Invoice Over Subcontract Warning Settings window, select the applicable fields.
4 In the Message Type dropdown, the choices are mutually exclusive. Select one of the following:
5 If you select Warning or Not Allow, you must select one of the following choices in the Tolerance Type list:
6 Once a Tolerance Type has been selected, enter the amount or percent for the type:
7 Click OK.

Links to more information . . .

More resources

For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.

For additional training on Sage products, visit Sage University.