During the life of projects, schedules will change. Maybe bad weather and unshipped materials have delayed one project. Another project is ahead of schedule because certain tasks were completed faster than expected. In both projects, changes to the duration of critical tasks could seriously impact other scheduled tasks or the completion date.
When you set the original schedule, Sage 100 Contractor copies the original duration, start date, finish date, and float data to the Original Duration, Original Start, Original Finish, and Original Float columns. By comparing the original schedule with the current schedule, you can determine what impact the changes are having on the project and make any necessary adjustments.
1 | Create the project schedule. |
2 | On the Options menu, click Original Schedule. |
Tip: If you made an error in the original schedule, you can modify the current schedule and reset the original.
|
For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.
For additional training on Sage products, visit Sage University.