You can bill for work and release holdbacks on the same application. After updating the application, remove the holdback rates.
1 | Open 3-9 Unitary Billing. |
2 | Do one of the following: |
3 | If you have issued change orders for the job, enter the approved changes. In the Change Quantity column, enter the quantity of units of change. |
4 | In the Current Quantity column, enter the quantity of units completed for each item. |
5 | On the menu bar, click Calculate. |
6 | Print the unitary bill application. |
7 | When you submit the unitary bill application, do the following: |
a | In the Submitted text box, enter the date you submitted the request. If you leave the Submitted text box blank, Sage 100 Contractor enters the current date for you. |
b | On the Options menu, click Submit Application. |
8 | After submitting the application, you can create an invoice by posting the application. On the Options, menu, click Post Application. |
9 | Prepare the next unitary bill application. |
Creating new unitary bills using Unitary Proposal |