The following are additional points to consider when setting up T&M jobs:

To set up a job for time and materials billing:

1 Open 3-10-1 T&M Billing Setup.
2 In the data control text box, enter the job number of the job you want to set up.
3 In the Wage Rate text box, enter the wage rate table you want to use.
4 In the Equipment Rate text box, enter the equipment rate table you want to use.
5 In the Hidden column, enter the markup rate that the customer does not see.

Note: T&M hidden markups do not increase the T&M invoice for labor if a wage rate is present.

6 In the Shown column, enter the markup rate.
7 In the Overhead column, enter the markup rate for overhead.
8 In the Profit column, enter the markup rate for profit.
9 In the Income Account text box, enter the ledger account number.
10 In the Subaccount text box, enter the subaccount number, as needed.
11 On the File menu, click Save.