Note: This functionality is available only if you have the Estimating Module.
| 1 | Open a takeoff in 9-5 Takeoffs. |
| 2 | Next to the Bid Item list, click the drop-down arrow and select a change order, or create a new change order if necessary. |
| 3 | If you are using phases, select the phase from the phase list or click to add a new phase item. |
| 4 | Do the following for each assembly or part that you want to reverse from the takeoff: |
| a | In the Assembly column, enter the assembly that you want to remove. |
| b | In the Part column, enter the individual parts that you want to remove. |
| c | In the Quantity column, enter a negative number. |
| 5 | Do the following for each assembly or part that you want to add to the takeoff: |
| a | In the Assembly column, enter the assembly number. |
| b | In the Part column, enter the part number for each individual part. |
| c | In the Quantity column, enter the quantity. |
| 6 | On the menu bar, click Calculate. |
| 7 | On the File menu, click Save. |
|
Exporting change orders from 9-5 Takeoffs to 6-4-1 Change Orders |
For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.
For additional training on Sage products, visit Sage University.