Note: This functionality is available only if you have the Estimating Module.
You can update part costs in a takeoff grid or an entire takeoff. Sage 100 Contractor updates the costs and vendors from the vendor preference list.
Important! Before saving, review the changes. After you save, you cannot reverse the update.
| 1 | Open a takeoff in 9-5 Takeoffs. |
| 2 | To update a specific grid, do the following: |
| 3 | Do one of the following: |
|
Updating part costs by average cost |
For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.
For additional training on Sage products, visit Sage University.