The Over Budget Warning command notifies you if costs exceed the budgeted amount for a job. When you select the Set Subcontract Over Budget Warnings option, Sage 100 Contractor determines the Actual + Committed costs to date for the job and phase by cost code and cost type.
It then compares the data to the original budget plus approved change orders. When you save the record, Sage 100 Contractor notifies you if costs exceed the budget plus approved change orders for a job and phase, cost code and cost type, plus the tolerance.
Notes:
| Message Type | Warning | 
| Tolerance Type | Flat amount | 
| Tolerance Amount | $100 | 
| Tolerance Percent | N/A | 
| Tolerance Amount Not To Exceed | N/A | 
 To set the Over Budget Warning
To set the Over Budget Warning       
            | 1 | In 6-7-1 Subcontracts, select Options > Set Over Subcontract Warning. | 
| 2 | In the Message Type dropdown, the choices are mutually exclusive. Select one of the following: | 
| 3 | If you select Warning or Not Allow, you must select one of the following choices in the Tolerance Type dropdown: | 
| 4 | Once a Tolerance Type has been selected, enter the applicable amount or percent for the type: | 
| 5 | Click OK. | 
| 
                             About displaying budget recaps How change orders affect budgets and proposals and subcontracts | 
For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.
For additional training on Sage products, visit Sage University.