This functionality is only available if you have the Equipment Module.
| 1 | Open 8-4 Equipment Allocation. |
| 2 | In the Date cell, enter the date of equipment use. |
| 3 | In the Description cell, enter a brief statement about the work. |
| 4 | In the Job cell, enter the job number. |
| 5 | In the Phase cell, enter the phase number. |
| 6 | In the Cost Code cell, enter the cost code number. |
| 7 | In the Operated Equipment cell, enter the equipment number. |
| 8 | In the Operated cell, enter the number of units that the equipment was operated. |
| 9 | In the Standby cell, enter the number of units that the equipment was on standby. |
| 10 | In the Idle cell, enter the number of units that the equipment was idle. |
| 11 | In the Rental Unit cell, enter the number for the type of unit by which you bill the equipment. |
| 12 | In the Operated Rental cell, enter the number of units for which you are billing. |
| 13 | In the Standby Rental cell, enter the number of units for which you are billing. |
| 14 | In the Idle Rental cell, enter the number of units for which you are billing. |
| 15 | Repeat steps 2–14 for each piece of equipment for which you want to create a cost record. |
| 16 | On the File menu, click Save. |
Tip: In the 6-3 Job Cost window, you can edit the equipment details that Sage 100 Contractor uses to create time and materials invoices.
|
Entering equipment costs for repair work |