Working with 9-Estimating (Parts and Assemblies) > 9-5 Takeoffs > Updating Parts Information > Updating part costs by average cost

Updating part costs by average cost

This functionality is available only if you have the Estimating Module.

You can update part costs in a takeoff grid or an entire takeoff. When you update, Sage 100 Contractor updates the cost using the average inventory cost from the parts database.

Caution! Always make a backup of your data before you update prices or add parts.

Important! Before saving, review the changes. After you save, you cannot reverse the update.

To update the part cost by average cost:

1 Open a takeoff in 9-5 Takeoffs.
2 To update a specific grid:
  1. In the Bid Item list, select the bid item.
  2. In the Phase list, select the phase.
3 Do one of the following: