Entering accounts payable invoices for subcontract lines

There are situations where you may need to invoice a portion of a subcontract. For example, you may want to invoice only the amount of one or more subcontract lines.

To enter a invoice for a portion of a subcontract:

1 Open 4-2 Payable Invoices/Credits.
2 In the Invoice# box, enter the invoice number.
3 In the Subcontract# text box, enter the contract number, and press the Enter key.
Information from the subcontract autofills the grid.
4 In the Description box, enter a description.
5 In the grid, locate the Quantity column, and then do one of the following:
6 Click the Automatically job cost while saving this record toolbar button.
7 Recall the record, and note the amounts displayed in the Invoice Total, Balance, and Net Due boxes located near the bottom-right of the window.
8 Open 6-7-1 Subcontracts, and recall the subcontract record that you partially invoiced.
9 Note the amounts in the Invoiced and Remaining Total boxes.