Consider these points:
1 | Open 3-8 Loan Draw Requests. |
2 | Using the data control, select the last application of the job and phase you want to update. |
3 | On the Update menu, point to Change Orders, and click Add to Existing Lines. |
4 | Repeat step 3 until you have resolved all cost codes. |
5 | On the menu bar, click Calculate. |
For additional online resources for Sage 100 Contractor products, visit the Sage Customer Portal. Use the portal to access the knowledgebase, chat online with customer support, or enter a customer support ticket.